Queen's Park Ontario Legislature Building
Several tonnes of stone were identified for replacement with St. Bee's sandstone from the U.K.
Several tonnes of stone were identified for replacement with St. Bee's sandstone from the U.K.
St Martin In The Fields Anglican Church, Toronto, Ontario
Phase 2
Martyn Masonry completed a restoration of the stone bell tower. In the fall of 2013, the Indiana limestone cross severed and dislodged tumbling to the slate roof below. We identified the reason for this failure and adjusted the new cross to prevent this from happening again.
The scope of work included:
Phase 2
Martyn Masonry completed a restoration of the stone bell tower. In the fall of 2013, the Indiana limestone cross severed and dislodged tumbling to the slate roof below. We identified the reason for this failure and adjusted the new cross to prevent this from happening again.
The scope of work included:
- cut/carve/install new Indiana limestone cross
- complete deep repoint of masonry
- replace substandard bricks
- sandblast/powdercoat bell bracketry
- replaced wooden/ferrous steel pulley system with brass and stainless steel pulley system
- cut/install new Indiana limestone jambstone
- cut/carve/install Dutchman on sill
St Andrew's Presbyterian, Toronto, Ontario
We subcontracted to Dj McRae Contracting on cut stone removal/installation and rubble wall rebuilds.
We subcontracted to Dj McRae Contracting on cut stone removal/installation and rubble wall rebuilds.
Gage Park, Hamilton, Ontario
- disassemble entire fountain
- complete cleaning
- 5 Dutchman repairs
- reassemble with new plumbing components
- replace stones on seat wall
- relay all stairs at watercourse.